12/02/2025 Reigart erect security fencing around the former club and demolish dangerous outbuildings at the back.
Stage 2 of demolition is still on for next winter, when the bats have flown. All the charity’s efforts will now be focused on fundraising to raise the remaining £50,000 needed to complete this.





07/02/2025 SGN find that their gas disconnection is already complete, so the work planned for next week is not now required. We’re further on than we thought!