30/01/2025  Preliminary gas disconnection work carried out by SGN

20/01/2025 Starling Learning confirm that neither the erection of the security fencing nor the demolition of the outhouses will disrupt wildlife. However as their ecology survey has identified the presence of a maternity bat roost in the main building, the former club itself cannot be demolished till around December 2025-January 2026

17/01/2025 Reigart given the go-ahead to put up security fencing and demolish outhouses. Timing to be confirmed

17/01/2025 CALA agree to pay for both security fencing and outhouse demolition from the fund they’ve awarded for demolition

09/01/2025 Extension of community exemption for water supply charges agreed with Clear Business (backdated to 1 April 2023)

07/01/2025 Permission requested for CALA Homes to pay for security fencing and outbuilding demolition from agreed demolition fund

07/01/2025 Quotation received from Reigart for the erection of security fencing and the demolition of outhouses at the back of the club building (these having become a health and safety concern)

03/12/2024 Very welcome donation received from AIS Vanguard’s Community Fund. Huge thanks to them!